PHASE 2

WORKS
UNDERWAY

The structure is complete to level 17 and continues upwards each week. By the middle of June, we should see the top more slender section of the building appear above level 21.

External fa├žade glazing is up to level 10, wrapping the building to create the indoor balconies. Levels 1 to 5 have internal walls and cabinets and bathrooms now complete as fit-out trades continue up the building.

PHASE 1

CONSTRUCTION
COMMENCED

The ground floor raft slab is now complete, and work has commenced on columns and walls up to level 1. Some sections of the ground floor slab at the front and rear of the site will be completed in future months. The next stage of works will see scaffold erected across the ground floor, and level 1 bubbledeck slabs landed in position.

PHASE 1 CONSTRUCTION COMMENCED 1/3 PHASE 1 CONSTRUCTION COMMENCED 2/3 PHASE 1 CONSTRUCTION COMMENCED 3/3