PHASE 1

CONSTRUCTION
COMMENCED

The ground floor raft slab is now complete, and work has commenced on columns and walls up to level 1. Some sections of the ground floor slab at the front and rear of the site will be completed in future months. The next stage of works will see scaffold erected across the ground floor, and level 1 bubbledeck slabs landed in position.