PHASE 1

CONSTRUCTION
COMMENCED

The ground floor raft slab is now complete, and work has commenced on columns and walls up to level 1. Some sections of the ground floor slab at the front and rear of the site will be completed in future months. The next stage of works will see scaffold erected across the ground floor, and level 1 bubbledeck slabs landed in position.

PHASE 1 CONSTRUCTION COMMENCED 1/3 PHASE 1 CONSTRUCTION COMMENCED 2/3 PHASE 1 CONSTRUCTION COMMENCED 3/3

PHASE 2

WORKS
UNDERWAY

Construction activities are now continuing on site with the main building structure rising above the ground floor. This includes the erection of precast concrete walls, forming up steelwork for in-situ concrete core walls and columns and craning in offsite made BubbleDeck floor panels.

Once everything is onsite and in place, concrete pours can occur, followed by the structure continuing up to the next floor and the process repeating. This occurs each couple of weeks.