PHASE 3

CONSTRUCTION
PROGRESSING

COMPLETION DUE EARLY 2023

The structure has reached level 23, indicating the commencement of the last phase of the structure as the tower form becomes more slender from here on.

We expect to see the roof deck level reached by late August with windows around the tower following closely behind, closing up the external balconies and allowing work to continue on internals. Cabinetry, tiling and finishing trades are on level 9 and the first few apartments are now complete.

VIEW FROM LEVEL 10 BALCONY 1/3 TYPE D1 APARTMENT | NORTH-EAST FACING 2/3 TYPE D1 APARTMENT | SCHEME A KITCHEN 3/3

PHASE 2

WORKS
UNDERWAY

The concrete structure for the building is up to level 9, currently rising in height one floor per week.

The lower floors forming the podium have external glazing now installed and apartments fronting Adelaide Terrace have internal walls and services commenced.

PHASE 2 WORKS UNDERWAY 1/3 PHASE 2 WORKS UNDERWAY 2/3 PHASE 2 WORKS UNDERWAY 3/3

PHASE 1

CONSTRUCTION
COMMENCED

The ground floor raft slab is now complete, and work has commenced on columns and walls up to level 1. Some sections of the ground floor slab at the front and rear of the site will be completed in future months. The next stage of works will see scaffold erected across the ground floor, and level 1 bubbledeck slabs landed in position.

PHASE 1 CONSTRUCTION COMMENCED 1/3 PHASE 1 CONSTRUCTION COMMENCED 2/3 PHASE 1 CONSTRUCTION COMMENCED 3/3